The Supreme Court of India recently issued a rule that explained how the limitation period must be determined for submitting an application to set aside an arbitral award in accordance with Section 34 of the Arbitration and Conciliation Act, 1996.
This ruling is significant because it addresses misunderstanding over time limits under arbitration law. On April 3, 2025, a bench consisting of Justice Pamidighantam Sri Narasimha and Justice Prashant Kumar Mishra rendered a decision in the case that was referred to as R.K. Transport Company v. Bharat Aluminum Company Ltd.
Their primary concern was determining whether or not a delay of a few days in the submission of the Section 34 application might be excused, particularly in cases where the deadline fell on a court holiday. The decision of the court not only concerns the rights of the parties, but it also reaffirms the correct interpretation of the limitation periods that are imposed by arbitration law.
For More Updates & Regular Notes Join Our Whats App Group (https://chat.whatsapp.com/DkucckgAEJbCtXwXr2yIt0) and Telegram Group ( https://t.me/legalmaestroeducators ) contact@legalmaestros.com.
Historical Context of the Case
The disagreement stemmed from a contract that was signed on April 1, 2002, between R.K. Transport Company and Bharat Aluminum Company Ltd. (BALCO) concerning the mining and transport of bauxite.
Due to disagreements on the payment, the subject was brought before an arbitrator. R.K. Transport Company was awarded Rs. 51.33 crores by the arbitral tribunal on April 9, 2022. The award was made in favor of the company from the beginning. BALCO received the award on the same day that it was signed and sent to them.
On July 11, 2022, BALCO submitted an application to contest the award in accordance with Section 34 of the Arbitration and Conciliation Act. This file was first approved by the trial court, which determined that the filing on Monday, July 11, was timely because the final day of limitation, which was July 9, was a Saturday and the following day was not until the following day, which was a Sunday.
After some time had passed, R.K. Transport Company submitted a request to recall this ruling, saying that the true last day for filing was July 8 and that it was a working day. BALCO’s application was deemed to be time-barred by the trial court, which concurred with the decision.
On the other hand, the High judicial reversed this ruling, stating that the submission was timely in accordance with Section 4 of the Limitation Act because July 9 was a holiday dedicated to the judicial system.
When the matter was brought before the Supreme Court, the question was whether or not the Section 34 application had been submitted within the legal limitation period.
Structure of the Law
The interpretation of Section 34(3) of the Arbitration and Conciliation Act was the primary focus of the legal dispute that was at the heart of the matter. The article in question specifies that a party has the ability to submit a request to set aside an arbitral award within three months of the date on which they received the verdict.
If adequate cause is established for the delay, the party is granted an additional thirty days to submit their request. Any application that goes beyond this point will not be considered.
In addition, the Limitation Act of 1963 was an important factor in this particular instance. Notable examples include the following:
There is a provision in Section 12 that permits the day that the award is received to be excluded.
In accordance with Section 4, the application may be submitted on the next business day in the event that the limitation period expires on a court holiday while the court is closed.
The most important question was whether or not these provisions of the Limitation Act apply to arbitration procedures that are conducted under Section 34.
Disputes between the Party Leaders
R.K. Transport Company, which was represented by senior attorney Mr. Mukul Rohatgi, maintained that the three-month time had ended on July 8, 2022 without any further action being taken.
Due to the fact that it was a working day, Section 4 of the Limitation Act did not apply, and the application that was submitted on July 11 occurred three days beyond the deadline. Furthermore, BALCO had not submitted any application to be excused from the delay; hence, the application had to be rejected because it was not submitted.
On the other hand, senior attorney Mr. Ranjit Kumar for BALCO contended that Section 12 of the Limitation Act permits the exclusion of the day the award was received. He said this during the course of his argument.
Because of this, the three-month term began on April 10, not April 9, which means that July 9 is the final day of the period. In accordance with Section 4 of the Limitation Act, the application that was submitted on Monday, July 11, was considered to be valid because the 9th of July was a Saturday and a court holiday.
The Analysis of the Supreme Court
Following a thorough examination of the statutory language of Section 34(3), the Court made the observation that the phrase “three months” is used rather than “ninety days.” In order to properly compute the period, it is necessary to use calendar months rather than fixed day counts. Earlier decisions, such as Himachal Techno Engineers and State of West Bengal v. Rajpath Contractors, had already provided clarification on this matter.
In addition, the Court upheld the applicability of Section 12(1) of the Limitation Act, which states that the date of receipt of the arbitral award is not included in the computation of the limitation period.
Following the receipt of the award on April 9, 2022, the limitation period started on April 10 of the same year. Because of this, the three-month period came to an end on July 9, which was a Saturday and the courts were both closed.
On the basis of Section 4 of the Limitation Act, the Court decided that in the event that the final day of filing falls on a holiday, the application may be submitted on the following day that the court is open for business. Therefore, the application that BALCO submitted on Monday, July 11, 2022, was submitted in a timely manner.
The court did not agree with the appellant’s contention that Section 12 should not be applied to arbitration cases, and it affirmed that the Limitation Act is not completely excluded from arbitration procedures. In its place, the applicability of each part is evaluated by taking into consideration the objective of arbitration law as well as the precise language of the provision that is under scrutiny.
What is the difference between “Three Months” and “Ninety Days”?
A considerable amount of the decision was devoted to elucidating the distinction between the terms “three months” and “ninety days.” Taking into consideration the fact that the terms “three months” and “ninety days” are not interchangeable in legal parlance, the Court vehemently rejected the viewpoint that the latter should be understood as the former.
In the Arbitration and Conciliation Act, the legislature purposefully used the phrase “three months,” which must be construed as three calendar months. This means that the number of days that make up those months can vary.
Because of this interpretation, all future arbitration cases will be affected, and procedural law will be brought into alignment with regular calendrical procedures.
Implications of the Decision
The order that the Section 34 application was filed in a timely manner and was legal was affirmed by the Supreme Court when it was brought before it. Additionally, it made it possible for the interim stay on the implementation of the arbitral ruling to continue being in effect while the case is being heard in the trial court.
Particularly considering that R.K. Transport had already withdrawn that portion of the judgment amount against a bank guarantee, the Court determined that there was no need to interfere with the High Court’s direction that BALCO should deposit only fifty percent of the whole amount of the award.
R.K. Transport Company’s appeal was not granted, since it was dismissed.
Expanded Legal Consequences
There are significant repercussions that this verdict will have for the law and practice of arbitration in India. The Court has offered clarification for legal practitioners and parties interested in arbitration by affirming that the requirements of the Limitation Act, such as Sections 4 and 12, apply to petitions filed under Section 34. In addition to this, it eliminates the possibility of procedural injustice occurring in the case that a deadline falls on a holiday.
In this decision, the importance of ensuring that procedural procedures are not utilized to unfairly undermine the rights of parties is emphasized. This is in line with the overarching goal of the Arbitration and Conciliation Act, which is to facilitate the resolution of disputes in a manner that is expedient, equitable, and most effective.
The decision that was handed down by the Supreme Court in the case of R.K. Transport Company v. Bharat Aluminum Company Ltd. contains authoritative clarification regarding the manner in which limitation periods are to be computed in accordance with arbitration law.
The Supreme Court struck a balance between procedural strictness and justice by defining “three months” as calendar months and allowed for court holidays to be excluded from this interpretation. Because of this finding, it will be easier to prevent needless litigation regarding technical timelines, and it will also ensure that valid claims are not rejected owing to small timing concerns.
The opinion of Justice Pamidighantam Sri Narasimha, which is based on sound reasoning, exemplifies the commitment of the judicial system to achieving both legal precision and equitable outcomes in commercial conflicts.